What do you mean by standard installation and non-standard installation?
Standard installation: When your parking spot location is such that the length of wiring from your meter to the parking is around 5 m, it’s a standard scenario for installation. The cost of cable, conduit and labour comes up to ₹1800 incl. of GST.
Non-standard installation: In case the distance between your parking spot and the meter is higher, and it demands wiring exceeding 5 m, it’s a non-standard scenario for installation. In this case, we charge on actuals i.e.extra wire, routing and the labor. Here is the cost for any extra work.
Cost of cable with conduit : ₹150 / extra meter
Cost of cabling without conduit: ₹90 / extra meter
New earthing connection: ₹3000 / pit
Load extension: Varies by area & load